Factory standard for control cabinet construction, m-Pro400SE Fastening System, pages 1 to 8

Pages 1 to 8 of 8

The original document is the PDF (172 KB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

For the Cooper STM12

Page 1

Instruction Manual P2054MA/EN 2011-04

Factory standard for control cabinet construction m-Pro400SE Fastening System

For additional product information visit our Web site at http://www.apextoolgroup.com

Page 2

About these assembly instructions Setup and assembly instructions for the m-Pro-400SE fastening system consisting of • Switch cabinet • Station controllerm-Pro-400SE • Built-in nutrunner series 1BB… to 4BB… • Hand tools series 18E…E… and 48E…E… • Tightening modules STM12, STM12 • Tightening modules STMH.1 for hand tools • Transformers for tightening modules • Cables • Switching elements (relays, etc.) A fastening system set up according to this factory standard fulfills all applicable safety and EMC standards and laws for industrial use. Detailed information on individual components P1713E

System overview modular fastening system

P2055MA

Assembly instruction Built-in nutrunner BB

P1544E

Tightening torques for installation of the Built-in nutrunner

P2037BA

Instruction manual for station controller m-Pro-400SE

P1671E

STMH.1 tightening module instruction manual

P1672E

Instruction manual for tightening modules STM12, STM34

P2102JH

Factory standard for cable installation

Symbols in text ➔

Identifies instructions to be followed.

•

Identifies lists.

Abbreviations m-Pro-400S(E)

Nutsetter control

Symbols in graphics: Identifies movement in a direction. Identifies function and force.

Disclaimer: CLECO reserves the right to modify, supplement or improve this document or the product without prior notice. This document may not be reproduced in whole or in part in any way, shape or form, or copied to another natural or machine-readable language or to a data carrier, whether electronic, mechanical, optical or otherwise, without the express permission of CLECO.

2

P2054MA/EN 2011-04

54a-en_Deckblatt.fm, 03.05.2011

Page 3

Contents 1

Establishment of earth and potential equalization

4

2

Conducting EMC Measures

5

3

Control cabinet measures

5

3.1 3.2 3.3

3.5 3.6

Control cabinet mounting plate ............................................................. 5 Installation of m-Pro-400SE station controller ...................................... 6 Installation of tightening modules STM12 and STM12 for built-in nutrunners 1BB... to 4BB... 6 Installation of tightening modules STMH.1 for hand tools 18E…E… and 48E…E… ............................................... 6 Transformers for tightening modules .................................................... 6 Switching elements (relays, etc.) .......................................................... 7

4

Cables

4.1

Cable laying .......................................................................................... 7

5

Mounting of built-in nutrunner and hand tools

3.4

P2054MA-EN_2011-04_Schaltschrankbau_m-Pro-400SEIVZ.fm, 03.05.2011P2054MA/EN 2011-04

7

7

3

Page 4

Establishment of earth and potential equalization

Install and wire all components according to the following chapters.

1

Establishment of earth and potential equalization

WARNING!

The system must not be operated without an attached protective earth (PE)!

Potential differences may occur between the electrical components during operation, caused by highfrequency interference currents. The resulting equalizing currents flow through the cable shields and interfere with signal lines. Corrective measures: ➔ Connect all components to an earth neutral point with potential equalization conductors (control cabinet mounting plate). ➔ Install the m-Pro-400SE station controller in the control cabinet door and ground it using a 1.5 qm protective earth on the rear connection. ➔ Using an earthing strap, connect the control cabinet door to the galvanized control cabinet mounting plate at the specified threaded bolt. ➔ Since the STM tightening modules are mounted on the control cabinet mounting plate, no further measures are necessary here. ➔ Connect the nutrunner mounting plate with the control cabinet mounting plate, order no. 960408-××× using a >10 mm2 earth line (yellow/green protective earth). ➔ Connect built-in nutrunners electroconductively with the nutrunner mounting plate. ➔ If there are multiple nutrunner mounting plates in a system, they must be connected to the control cabinet mounting plate in a star-shaped configuration.

STM12

STM12 Clamp shielding braid across large area!

Station controller m-Pro-400SE

Transformer only if necessary

Built-in nutrunner Series …BB…

Nutrunner mounting plate

Hand tool 18E…E… / 48E…E… a00252_2.wmf

1

Fig. 1-1

4

P2054MA/EN 2011-04

54b-en_Montageanleitung.fm, 03.05.2011

Page 5

Conducting EMC Measures

2

Conducting EMC Measures NOTE

This is a class A device. This device may cause radio interference in residential areas; should this occur, you may request that the operator pay for and implement relevant EMC measures. ➔ The system may only be operated with the control cabinet closed. The properties of the shielding would be altered and the noise emission increase. • • •

The filters, mains filters, motor output filters and filters on the input and output plug connections necessary for compliance with the EMC regulations are integrated into the devices. The closed control cabinet and shielded cable provide very good protection against irradiated and radiated interference. Disturbances by other electrical components must be inspected by the control cabinet assembler. EMC-compliant setup of the control cabinet is required.

Examples ➔ ➔ ➔ ➔ ➔ ➔ ➔

3

Control cabinet measures ➔ ➔

3.1

Keep earth connection points large in size and free of paint. Use an earthing strap with a large cross section. Fasten transformers on a conductive, galvanized control cabinet mounting plate across the largest possible area. Attach protective circuits as closely to the disturbance source (relay, valve ...) as possible. Mount filters directly to galvanized and grounded mounting plate. Don't lay input and output lines in parallel to each other. Place line crossings as perpendicularly as possible and with sufficient space between lines that emit interference and lines that are sensitive to interference.

Use a closed steel-sheet control cabinet (IP54). Connect all movable control cabinet parts with the control cabinet mounting plate using earthing straps.

Control cabinet mounting plate ➔

Use a galvanized, unpainted, steel mounting plate. The mounting plate serves as a neutral earth point.

54b-en_Montageanleitung.fm, 03.05.2011

P2054MA/EN 2011-04

5

2

Page 6

3

Control cabinet measures

3.2

Installation of m-Pro-400SE station controller ➔ ➔ ➔ ➔

3.3

Installation of tightening modules STM12 and STM12 for built-in nutrunners 1BB... to 4BB... ➔ ➔ ➔ ➔ ➔ ➔

3.4

➔ ➔ ➔ ➔ ➔ ➔

Refer to the STMH.1 tightening module instruction manual. No extreme filter measures are necessary due to integrated mains filters. Screw tight tightening modules on galvanized and grounded nutrunner mounting plate using two M6 screws. Connect protective earth (PE) at connection XS1 pin 3. Power can be supplied via an isolated transformer (see 3.5 Transformers for tightening modules, page 6). The transformer can be ungrounded on the secondary side, protection class 1. Install an FI circuit breaker as an additional protective measure. Use STMH.1 tightening module only with CLECO hand tools.

Transformers for tightening modules ➔ ➔

➔

➔

➔ ➔

6

Refer to the STM12, STM12 tightening module instruction manual. No extreme filter measures are necessary due to integrated mains filters. Screw tight tightening modules on galvanized and grounded nutrunner mounting plate using two M6 screws. Connect protective earth (PE) at connection XS1 pin 3. If transformers are used, ground them at the neutral point on the secondary side. Only use tightening modules with CLECO series BB built-in nutrunners.

Installation of tightening modules STMH.1 for hand tools 18E…E… and 48E…E… ➔

3.5

Refer to m-Pro-400SE station controller instruction manual. Install the m-Pro-400SE station controller in the control cabinet door and ground it using a 1.5 qm protective earth on the rear connection. Using an earthing strap, connect the control cabinet door to the galvanized control cabinet mounting plate at the specified threaded bolt. When operating the m-Pro-400SE station controller, the control cabinet must be closed.

Only use isolation transformers according to IEC 742 or EN 60742. Only transformers authorized by CLECO must be used. Only these transformers fulfill the parameters important for the tightening technology, such as rigidity and overload capacity. If the STM12 and STM12 tightening modules are powered using a 3-phase transformer, the secondary neutral point of the transformer must be grounded. Only with this measure can the tightening module detect and shut off any potentially occurring short circuit between the motor phase and earth (e.g. in the cable or motor). With a cable length exceeding 20 m, the power supply of the STMH.1 tightening module (for hand tools) is wired with an isolation transformer. The secondary neutral point is not grounded due to safety reasons. This applies to 1-phase and 3-phase transformers. If STMH.1 is used beside STM12 or STM12 in a control cabinet, the power supplies must be realized as described above. Screw the transformers tight to the control cabinet mounting plate. If this is not possible, the mounting plate of the transformer must be connected with the control cabinet mounting plate using an earthing strap.

P2054MA/EN 2011-04

54b-en_Montageanleitung.fm, 03.05.2011

Page 7

Cables

3.6

Switching elements (relays, etc.) ➔

4

Always use spark suppressors with relays, switching elements and valve coils. They reduce the number of internally-caused disturbances.

Cables ➔ ➔ ➔

4.1

Refer to the "Cable laying factory standard" installation information. Only cables or cable types authorized by CLECO may be used. Adhere to maximum cable length - Built-in nutrunner and hand tools = 50 m. - Hand tools without transformer = 20 m. - ARCNET cables = 100 m.

Cable laying ➔ ➔

Don't use extra-long cables and wires (reserve). Avoid mutual interference. Lay so-called "hot" and "cold" signal lines separately. For this, use cable ducts in the control cabinet that are physically separated from each other.

"Hot" signal lines

Motor cable, spindle cable, mains, controller power supply, cooling unit

"Cold" signal lines

24 VDC, PE, ARCNet cable, bus cable, resolver lines, separate cables from transducers

NOTE ➔

5

Don't lay "hot" and "cold" signal lines in parallel to each other.

Mounting of built-in nutrunner and hand tools ➔ ➔ ➔ ➔ ➔

Refer to System overview modular fastening system. Only CLECO built-in nutrunners and hand tools must be used. Connect the nutrunner mounting plate with the control cabinet mounting plate using a >10 mm2 earth line (yellow/green protective earth). Connect built-in nutrunners electroconductively with the nutrunner mounting plate. The hand tools are classified according to "Protection class I". Connect all conductive housing parts with the protective earth.

54b-en_Montageanleitung.fm, 03.05.2011

P2054MA/EN 2011-04

7

4

Page 8

Sales & Service Centers Note: All locations may not service all products. Please contact the nearest Sales & Service Center for the appropriate facility to handle your service requirements. Dallas, TX Apex Tool Group Sales & Service Center 1470 Post & Paddock Grand Prairie, TX 75050 Tel: 972-641-9563 Fax: 972-641-9674

Detroit, MI Apex Tool Group Sales & Service Center 2630 Superior Court Auburn Hills, MI 48326 Tel: 248-391-3700 Fax: 248-391-7824

Houston, TX Apex Tool Group Sales & Service Center 6550 West Sam Houston Parkway North, Suite 200 Houston, TX 77041 Tel: 713-849-2364 Fax: 713-849-2047

Lexington, SC Apex Tool Group 670 Industrial Drive Lexington, SC 29072 Tel: 800-845-5629 Tel: 803-359-1200 Fax: 803-358-7681

Los Angeles, CA Apex Tool Group Sales & Service Center 15503 Blackburn Avenue Norwalk, CA 90650 Tel: 562-926-0810 Fax: 562-802-1718

Seattle, WA Apex Tool Group Sales & Service Center 2865 152nd Avenue N.E. Redmond, WA 98052 Tel: 425-497-0476 Fax: 425-497-0496

York, PA Apex Tool Group Sales & Service Center 3990 East Market Street York, PA 17402 Tel: 717-755-2933 Fax: 717-757-5063

Canada Apex Tool Group Sales & Service Center 5925 McLaughlin Road Mississauga, Ont. L5R 1B8 Canada Tel: 905-501-4785 Fax: 905-501-4786

Germany Cooper Power Tools GmbH & Co. OHG a company of Apex Tool Group, LLC Postfach 30 D-73461 Westhausen Germany Tel: +49 (0) 73 63/ 81-0 Fax: +49 (0) 73 63/ 81-222

England France Cooper Power Tools Cooper Power Tools SAS a company of a company of Apex Tool Group, LLC Apex Tool Group, LLC Unit G Quinn Close Zone Industrielle Seven Stars Industrial Estate BP 28 Whitlet Avenue Maurice Chevalier Coventry CV3 4LH 77831 Ozoir-la-Ferrière Cedex England France Tel: +44-2476-3089 60 Tel: (011) 33 1 64 43 22 00 Fax: +44-2476-3089 69 Fax: (011) 33 1 64 40 17 17

Mexico Cooper Tools de México S.A. de C.V. a company of Apex Tool Group, LLC Vialidad El Pueblito #103 Parque Industrial Querétaro Querétaro, QRO 76220 Tel: +52 (442) 211-3800 Fax: +52 (442) 103-0443

Brazil Cooper Tools Industrial Ltda. a company of Apex Tool Group, LLC Av. Liberdade, 4055 Zona Industrial - Iporanga 18087-170 Sorocaba, SP Brazil Tel: (011) 55 15 238 3929 Fax: (011) 55 15 228 3260

Apex Tool Group, LLC 1000 Lufkin Road Apex, NC 27539 Phone: 919-387-0099 Fax: 919-387-2614 www.apextoolgroup.com

China Cooper (China) Co., Ltd. a company of Apex Tool Group, LLC 955 Sheng Li Road, Heqing Pudong, Shanghai China 201201 Tel: +86-21-28994176 Fax: +86-21-51118446