Page 41

Power Management Services Features • System design and bill of material recommendations • Remote power switching system design • Develop specifications, drawings, and documentation • Automatic control systems/PLC ladder programming, including load shed/ peak shaving schemes

• Custom hardware/ software solutions • Third party communications interfaces • Configured workstations, user software interfaces • On-site installation assistance, component configuration, and startup

• On-site and headquarters-based customer training • Troubleshooting assistance, support for hardware and software products • Product upgrades • Project coordination

• Panelboard low-voltage wiring verification

Power Management Services provides a complete range of design and operational services, including specifying, developing, installing, commissioning, supporting, and training users of power monitoring and control system and remote power switching systems. Engineers maintain expertise in many areas such as communications, personal computers, protective relaying, automatic control systems, and programmable controllers. POWERLINK Workstations Square D offers a complete systems approach to lighting control. Power Management Services provides POWERLINK workstations - tested and approved personal computers completely configured based on the individual system requirements. POWERLINK workstations are designed to handle large amounts of system information, and provide it to those who need it, when they need it. Workstations placed in key locations allow plant engineers allow plant engineers, operators, maintenance personnel, and others to make informed decisions using real-time and historical information. Power Management Operation Technical Support There are several ways to receive top quality support on POWERLOGIC and POWERLINK products: • Phone: 615-287-3400 • Fax: 615-287-3404 • BBS: 615-287-3414 • Email: pmosuprt@squared.com • D-Fax: 800-557-4556 (PMO index is Document #104)

42

SQUARE D

9/98

Page 42

Compliance Certification Codes and Standards Square D panelboards are designed, tested, and manufactured to meet the requirements of the latest revisions of the following standards: UL 67, Panelboards UL 50, Enclosures for electrical equipment UL 489, Molded Case Circuit Breakers UL 917, Energy Management Equipment CSA C22.2, No. 29, Panelboards and Enclosed Panelboards CSA C22.2, No. 5, QO(B) Only, Molded Case Circuit Breakers NEMA PB–1 NEMA AB–1, Molded Case Circuit Breakers NFPA 70, National Electrical Code Federal Specification W-P-115C Type 1 Class 1 Federal Specification W-C-375B/GEN NOM 117 (pending final testing) California Title 24

SQUARE D

9/98

43

Page 43

Compliance Certification Year 2000 Compliance POWERLINK AS Remote Power Switching System Testing has been successfully conducted on currently available POWERLINK AS hardware and software to handle the Year 2000 transition. Testing was conducted using panels with version 4.50 firmware, version 2.00 PLK-101 software and version 1.01 CMS-1000 configuration software. Users are encouraged to make these upgrades to their POWERLINK systems. Registered users may obtain free upgrades by contacting Power Management Operations Technical Support. Hardware Evaluation POWERLINK uses year data for calculation of the day of the week only. Tests have verified that operation is correct at the transition into the next millennium. Testing has also verified that the Year 2000 is treated correctly as a leap year. The year is represented and stored internally in a two-digit format, i.e., 1999 = 99, 2000 = 00. The real-time clock chip used in the device only allows a two-digit year. The program interprets these digits in such a way that any year below 95 is assumed to occur after the year 2000. HARDWARE

Compliant

AS42C-T v4.50 2

Yes

AS42CM-T v4.50 2

Yes

Software Evaluation The only function of POWERLINK software in regards to the year is to provide the ability to set or review the year data within a POWERLINK panelboard. The year data is not used for any calculations within the software. Testing has verified that operation of PLK-101 and CMS-1000 software packages in conjunction with a POWERLINK panelboard is correct before and after the Year 2000. The format used in the software is consistent with the two-digit year representation used in the panelboard. The only place a four-digit year appears is where the PC time and date is displayed on the year screen used to set the clock. The first two digits of the PC year are truncated when sent to the panelboard. SOFTWARE

Compliant

PLK-101 v2.00

Yes

CMS-1000 v1.01

Yes

Additional Evaluation Testing on POWERLINK panelboards with v3.02 System Manager 3000 software was also conducted. Results of this testing was also successful.

44

SQUARE D

9/98

Page 44

Suggested Specifications SECTION 16440-1 PANELBOARD LIGHTING CONTROL SYSTEM PART 1 GENERAL 1.01 SYSTEM DESCRIPTION A. The panelboard lighting control system shall automatically control lighting and other loads within the facility. B. The system shall be used as a [stand-alone], [networked] system for controlling loads via external low voltage inputs, and/or from its [internal time-of-day clock]. C. The system shall include branch circuit overcurrent protection and remote power switching, low voltage switch inputs, control logic functionality and shall all fit within a standard lighting panelboard enclosure. D. To assure seamless integration, all major system components shall have a common manufacturer. 1.02 REFERENCES A. Required UL Listings: UL 489 for Molded Case Circuit Breakers, UL 67 for Panelboards, UL 50 for Boxes and Enclosures, and UL 916 for Energy Management Equipment. B. NEMA Compliance: PB-1 for Panelboards C. NEC 110-10 Compliance D. FCC Approval: All assemblies are to be in compliance with FCC Emissions Standards specified in Part 15 Subpart J for Class A applications. 1.03 SYSTEM START-UP AND TRAINING [OPTIONAL] A. Start-Up: After the system has been installed, and the documentation delivered to the owner, the contractor shall secure the services of a factory trained manufacturerís representative for [__] day(s) to verify correct operation of all system components. B. Training: At system start-up, the contractor shall arrange for the factory representative to train the owner’s personnel. C. Factory Support: Factory fax/telephone support shall be available free of charge during normal business hours to answer programming and application questions during the warranty period. 1.04 WARRANTY Manufacturer shall warrant specified equipment to be free from defects in materials and workmanship for the lesser of one year from the date of installation or eighteen months from date of purchase. PART 2 PRODUCT 2.01 MANUFACTURERS The panelboard lighting control system shall be POWERLINK AS as manufactured by Square D Company [or pre-approved equal; preapproval shall entail submitting a fully functional sample of the product to the engineer at least 3 weeks prior to bid. The sample shall include all options required to meet the specification]. 2.02 PANELBOARD LIGHTING CONTROL SYSTEM A. The lighting control system shall consist of a microprocessor-based control electronics with remotely operated circuit breakers. SQUARE D

9/98

45

Page 45

Suggested Specifications B. The circuit breakers shall provide overcurrent protection meeting or exceeding the fault current of the system to which the panelboard is being applied. C. The lighting control system shall meet or exceed the following capabilities: 1. Individual remote control for 42 branch circuits. 2. Up to sixteen 2-wire maintained dry-contact inputs for connection to external low voltage (24 VDC or below) switch contacts. 3. Zone creation of multiple branch circuits and control of individual branch circuits or zones. 4. Individual branch circuit and zone override. 5. True closed loop control by monitoring branch circuit breaker status based on actual system voltage at load side terminal. 6. Downloadable firmware that will permit field installation of newest features in existing systems. D. All lighting control components shall be installed in a conventional panelboard enclosure. Suitable barriers between Class 1 and Class 2 wiring shall be provided. 2.03 HARDWARE A. To minimize installation labor and space requirements, the remote operated circuit breakers, power interface module, and control module shall be integral to the lighting panelboard. B. Remotely operated circuit breakers: All remotely operated branch circuit breakers shall provide overload and short circuit protection suitable for that location in the electrical system, as defined in the panelboard schedules. Remotely operated power switching devices shall provide the following: 1. Load switching endurance rating of 200,000 open/close operations at full load and 0.8 lagging power factor. 2. Switching devices with lower endurance ratings may be judged to be acceptable, but must be provided with [100%] [200%] spare switching devices for each circuit to ensure an equivalent total number of operations. 3. 15A, 20A, and 30A current ratings. 4. Integral branch circuit overcurrent protection as required by the National Electrical Code (NEC), and shall be either fully rated or shall have published series connected ratings for providing adequate protection at that point in the system. 5. Available in single-, two-, and three-pole configurations. 6. UL Listing SWD rating on 15A and 20A 1-, 2- and 3-pole branches; UL Listed HACR rating and UL Listed HID rating on all remotely operated power switching devices. 7. Handle that mechanically opens power switching device contacts when moved to the OFF position and disables remote control capabilities of the device. 8. Operating mode selector button on each power switching device shall be provided to enable or disable remote operated function of the device independent of the handle. 9. Visible flag to clearly indicate the status of the circuit breaker contacts. a. Status condition shall include: ON, OFF, TRIPPED. b. The visible flag shall be mechanical in nature, directly tied to the breaker mechanism, and shall be provided in addition to any 46

SQUARE D

9/98

Page 46

Suggested Specifications status indicator supplied by the system electronics. c. Switching devices not equipped with such an indicator shall be equipped with an alarm and auxiliary contacts [wired to LED or neon pilot lights] [suitable for wiring to external pilot devices]. 10. All individual power switching devices rated for 120/240 or 208Y/120 VAC shall have a short circuit interrupting rating of 10,000 rms symmetrical amperes. 11. All individual power switching devices rated for 277 or 480Y/277 VAC shall have a short circuit interrupting rating of 14,000 rms symmetrical amperes, or 65,000 rms symmetrical amperes at 120 or 208Y/120 VAC. 12. Power switching devices shall meet all NEC requirements for circuit breakers; shall be UL Listed as circuit breakers. C. All electronic modules and circuit breakers in the panelboard shall be mounted in the positions and control the loads as indicated on the panelboard drawings. D. Panelboards shall accept standard circuit breakers for loads not controlled by the system. E. Interconnections: All interconnections between circuit breakers, control buses and power interface modules shall meet NEC and UL requirements for Class 1 control circuits. F. Modular control buses shall be used to provide control power and communications to the remote operated branch breakers. G. Power Interface Module: A Power interface module shall be provided to supply control power for the operation of the remotely operated circuit breakers, power for low voltage inputs, and power for the electronics and communications. The module shall provide screw type terminals for up to sixteen 2-wire maintained or 2-wire momentary inputs, or eight 3-wire momentary inputs for connection to external low voltage (24 VDC or below) switch contacts. H. Control Module [Optional, Required if using RS-485 network]: A control module shall be provided where indicated. 1. The control module shall provide time clock, communications, and programming functionality. 2. There are two front panel display options: [select a. or b. and the respective quantity]. a. Standard control module has LEDs that permit setup of communications address and baud rate, and displays basic operating mode and status information. [Provide one (1) standard control module to program all lighting control panelboards on a job site; provide a standard control module for each lighting control panelboard]. b. Display control module shall have high-resolution graphics LCD display and keypad that will permit programming of the system, control override of the breaker status, give electronic indication of the breaker status, and display diagnostic information at the front panel. [Provide one (1) display control module to program all lighting control panelboards on a job site; provide a display control module for each lighting control panelboard]. 3. The control module with time-of-day control shall meet or exceed the following capabilities: a. Ability to execute up to 4 daily schedules. b. 365-day calendar with automatic leap year correction, and daylight savings time adjustment. c. Astronomical clock with sunrise/sunset SQUARE D

9/98

47

Page 47

Suggested Specifications d. 7-day repeating schedule e. 12-hour AM/PM or 24-hour military time format f.

32 special holiday/event periods g. Programmable sequence delay of circuit breakers h. Local display of day/date/time (with available LCD display) i.

Adjustable timer for inputs (time overrides)

j.

Priority maintained inputs k. Adjustable flash notice assignable to time-of-day or timed inputs commands l.

Capacitor back-up power for time clock back up for 30 days.

4. The control module shall have downloadable firmware so that the latest production features may be added in the future without replacing the module. 2.04 NETWORK [OPTIONAL] A. [RS-485 network] option shall enable the panelboard lighting control system to connect with other control systems. B. User may set up, monitor, and control any panelboard connected to the network from a remote workstation. C. Network shall be configured to support all panelboards and personal computer workstations as required. D. [LonWorks] compliant network shall be required to provide interoperability between the lighting control panelboards such that inputs or switching events in one panel may be used to control the switching of breakers in another panel. This interoperability shall be not be limited to panelboards, but shall extend to any LonWorks compliant device such as occupancy sensors or network switches. 2.05 SOFTWARE [OPTIONAL] A. The software shall provide a user-friendly interface for set-up and maintenance of input-based and time-based schedules. B. Software shall provide remote monitoring and control of the system or individual remotely operated circuit breakers. C. Operates on a Windows 3.1/Windows 95 platform. 2.06 PERSONAL COMPUTER WORKSTATIONS [OPTIONAL] A. The lighting panelboard system shall include personal computer workstations complete with software as specified in section 2.05 of this specification. The workstation(s) shall be pre-configured with all software, configuration files and ready to connect and operate when delivered to the job site. B. The panelboard lighting control system shall include [__] factory supplied personal computer workstations. C. Each workstation shall consist of a Pentium II or higher CPU, color monitor, Windows 3.1, Windows 95, network interface card, CD-ROM, and/or [3.5 in.] floppy drive, [__] Mbytes RAM and [__] Mbytes hard drive storage. 3.01 EQUIPMENT INSTALLATION AND DOCUMENTATION INSTALLATION A. The panelboard lighting control system with remotely operated circuit breakers shall be installed and wired completely as shown on the plans by the contractor. 48

SQUARE D

9/98

Page 48

Suggested Specifications B. All remote control wiring shall be installed in accordance with Article 725, Class 2 of the National Electrical Code and local codes. C. Wire size shall be as recommended by manufacturer, but shall not be smaller than #24 AWG. D. Install system in accordance with manufacturerís written instructions and the NEC. E. Contractor shall coordinate all of the work in this section with all of the trades covered in other sections of the specification to provide a complete and operable system. END OF SECTION

SQUARE D

9/98

49

Page 49

Square D, , POWERLINK, POWERLOGIC, SY/MAX, SY/NET, SY/LINK are registered trademarks of Square D Company. System Manager and CircuitManager are trademarks of Square D Company. All other product names listed in this document are trademarks of their respective companies. Bulletin No. 1210CT9801

September, 1998