Browse
(440) 299-7778
Menu
(440) 299-7778
One-year parts and labor warranty30-day money-back guaranteeContact

The text of a manual · part 14 of 26

SLC 500 Fixed Hardware Style (Cat. No. 1747-L20, 1747-L30, and 1747-L40 Processors) Installation and Operation Manual, pages 113 to 121

Pages 113 to 121 of 223

The original document is the PDF (1.7 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

For the Allen-Bradley 1747-L20A, Allen-Bradley 1747-L20B, Allen-Bradley 1747-L20C, Allen-Bradley 1747-L20L, Allen-Bradley 1747-L30D, Allen-Bradley 1747-AIC and Allen-Bradley 1747-L40C

Page 113

Appendix A Setting Up the DH-485 Network

Setting Node Addresses The best network performance occurs when node addresses start at 0 and are assigned in sequential order. SLC 500 processors default to node address 1. The node address is stored in the processor status file (S:15L). Processors cannot be node 0. Also, initiators such as personal computers should be assigned the lowest numbered addresses to minimize the time required to initialize the network. If some nodes are connected on a temporary basis, do not assign addresses to them. Simply create nodes as needed and delete them when they are no longer required. Setting Processor Baud Rate The best network performance occurs at the highest baud rate, which is 19200. All devices must be at the same baud rate. The default baud rate for SLC 500 devices is 19200. The baud rate is stored in the processor status file (S:15H). Maximum Node Address Setting The maximum node address parameter should be set as low as possible. This minimizes the amount of time used in soliciting successors when initializing the network. If all nodes are addressed in sequence from 0, and the maximum node address is equal to the address of the highest addressed node, the token rotation will improve by the amount of time required to transmit a solicit successor packet plus the slot timeout value. Note that this does not allow any node to be added to the network without affecting the response time. On the other hand, since the time required to hold an open station address is greater than the time required to pass a token, it can be useful to leave a temporary device (such as a personal computer) connected if there is only one such device. (A solicit successor packet requires the same transmission time as the token pass, but there is an added slot timeout period.) See the Hand–Held Terminal User Manual, Catalog Number 1747–NP002, or the Advanced Programming Software User Manual, Catalog Number 1747–NM002, for the procedures to set node addresses, processor baud rate, and maximum node addresses. Important: The SLC 500 Series A (only) processors set the maximum node address to 31 when power is cycled increasing initialization and response time of the network.

A–8

Page 114

Appendix A Setting Up the DH-485 Network

DH-485 Network Installation

To install a DH–485 network, you will need tools to strip the shielded cable and to attach the cable and terminators to the isolated link coupler. Install the DH–485 network using the following tools (or equivalent): Description

Part Number

Manufacturer

Shielded Twisted Pair Cable

#9842

Belden

Stripping Tool

45-164

Ideal Industries

1/8 " Slotted Screwdriver

NA

NA

DH-485 Communication Cable and Isolated Link Coupler The link coupler provides a connection for each node. The isolated link coupler electrically isolates the DH–485 communication interface from the processor and peripheral connections. Electrical–optical isolation is provided to 1500 VDC. The suggested DH–485 communication cable is Belden #9842 cable. The cable is jacketed and shielded with two twisted wire pairs and a drain wire. One pair provides a balanced signal line, and one wire of the other pair is used for a common reference line between all nodes on the network. The shield reduces the effect of electrostatic noise from the industrial environment on the network communication.

A–9

Page 115

Appendix A Setting Up the DH-485 Network

Installing the DH-485 Communication Cable The communication cable consists of a number of cable segments daisy–chained together. The total length of the cable segments cannot exceed 1219 m (4000 ft). When cutting cable segments, make them long enough to route them from one link coupler to the next with sufficient slack to prevent strain on the connector. Allow enough extra cable to prevent chafing and kinking in the cable. Belden #9842

Belden #9842

Belden #9842

Link Coupler 1747-AIC

Link Coupler 1747-AIC

Link Coupler 1747-AIC

DH-485 Interface

DH-485 Interface

DH-485 Interface

Peripheral

Connector

Peripheral

Connector

Peripheral

CPU

CPU

CPU

Power

Power

Power

Connector

Important: We only recommend a network that is daisy–chained. For example, we do not recommend the following: Belden #9842

Belden #9842

Belden #9842

Connector

Connector

Connector

Incorrect

A–10

Page 116

Appendix A Setting Up the DH-485 Network

Connecting the Communication Cable to the Isolated Link Coupler Attach the terminal block of the link coupler to the Belden #9842 cable as shown below. Additional terminal blocks are available for replacement, see chapter 9. Single Cable Connection Orange with White Stripes Belden #9842

Shrink Tubing Recommended

White with Orange Stripes

Blue with White Stripes Drain Wire

6 5 4 3 2 1

Termination A B Common Shield Chassis Ground

Multiple Cable Connection to Previous Device to Successive Device

19525

A–11

Page 117

Appendix A Setting Up the DH-485 Network

The table below shows wire/terminal connections for DH–485 connectors for old Belden #9842. For this Wire/Pair Shield/Drain Black/White

Black/Red

Connect this Wire

To this Terminal

Non-jacketed

Terminal 2 - Shield

Black

Cut back - no connection➀

White

Terminal 3 - (Common)

Black

Terminal 4 - (Data B)

Red

Terminal 5 - (Data A)

➀ To prevent confusion when installing the communication cable, cut back the black wire immediately after the the insulation jacket is removed. This wire is not used by DH-485.

The table below shows wire/terminal connections for DH–485 connectors for new Belden #9842. For this Wire/Pair Shield/Drain Blue/White

White/Orange

Connect this Wire

To this Terminal

Non-jacketed

Terminal 2 - Shield

White with Blue Stripe

Cut back - no connection➀

Blue with White Stripe

Terminal 3 - (Common)

White with Orange Stripe

Terminal 4 - (Data B)

Orange with White Stripe

Terminal 5 - (Data A)

➀ To prevent confusion when installing the communication cable, cut back the white with blue stripe wire immediately after the the insulation jacket is removed. This wire is not used by DH-485.

Important: In Series A 1747–AIC, terminal 5 was called DATA B and terminal 4 was called DATA A. In this case, use terminal numbers only and ignore signal names DATA B and DATA A. The internal circuitry of the Series A is the same as Series B.

A–12

Page 118

Appendix A Setting Up the DH-485 Network

Grounding and Terminating the DH-485 Network One (only one) of the link couplers at the end of the link must have Terminals 1 and 2 of the network connector jumpered together. This provides an earth ground connection for the shield of the communication cable. Link couplers at both ends of the network must have Terminals 5 and 6 of the link connectors jumpered together. This connects the termination impedance (of 120Ω) that is built into each link coupler as required by the DH–485 specification. See the figure below for the proper jumpering.

End-of-Line Termination Jumper

Jumper Belden #9842 Cable (1219 m) 4000 ft Maximum

6 5

6 5 4

4

3

3

2

2

1

1 Jumper

A–13

Page 119

Appendix A Setting Up the DH-485 Network

Powering the Link Coupler In normal operation with the programmable controller connected to the link coupler, the processor powers both the link coupler and peripheral device (DTAM, PIC, HHT), if connected, through the C11 cable. If you do not connect the processor to the link coupler, then use a 24 VDC power supply to power the link coupler and peripheral device. The 1747–AIC requires 85mA at 24 VDC. With a peripheral device connected, the total current required is 190mA at 24 VDC. If both the processor and external power are connected to the link coupler, only the external source is used. Important: Always connect the CHS GND (chassis ground) terminal to the nearest earth ground. This connection must be made whether or not an external 24 VDC supply is used. Below are three options for externally powering the 1747–AIC: • If the link coupler is to be installed in an office environment, you can use the wall mount power supply (1747–NP1) or global desktop power supply (1747–NP2). The link coupler would be powered through either the 1747–C10 cable or by hardwiring from the supply to the screw terminals on the link coupler. • If you use the AC chassis power supplies (1746–P1 or 1746–P2), you can use the 24 VDC user power supply (200mA maximum) built into the power supply. The link coupler would be powered through a hard–wired connection from the screw terminals on the power supply to the screw terminals on bottom of the link coupler. • You can use an external DC power supply with the following specifications: – operating voltage: 24 VDC + 25% – output current: 190mA – rated NEC The link coupler would be powered through a hard–wired connection from the external supply to the screw terminals on the bottom of the link coupler.

!

A–14

ATTENTION: If you use an external power supply, it must be 24 VDC. Permanent damage will result if miswired with the wrong power source.

Page 120

Appendix A Setting Up the DH-485 Network

The figure below shows the external wiring connections and specifications of the link coupler.

SLC 500 DH–485 LINK COUPLER CAT

SER

LISTED IND. CONT. EQ. FOR HAZ. LOC. A196

Left Side

OPERATING TEMPERATURE CODE T3C

CLASS 1, GROUPS A, B, C AND D, DIV. 2 6 TERMINATION 5 A 4 B 3 COMMON 2 SHIELD 1 CHASSIS GROUND

EXTERNAL POWER REQUIREMENTS 24 VDC +/– 25% AT 190 mA N.E.C. CLASS 2

CAUTION – EXTERNAL POWER, IF USED, MUST BE 24VDC PERMANENT DAMAGE TO CIRCUITRY WILL RESULT IF MISWIRED WITH THE WRONG POWER SOURCE. . 24VDC

DC NEUT CHS GND

FAC 1P

MADE IN U.S.A.

CHS GND

DC NEUT

24 VDC

Bottom

A–15

Page 121

Appendix A Setting Up the DH-485 Network

You can connect an unpowered link coupler to the DH–485 network without disrupting network activity. In addition, if an SLC 500 controller powers a link coupler that is connected to the DH–485 network, network activity will not be disrupted should the SLC 500 controller be removed from the link coupler.

Installing and Attaching the Link Couplers 1. Take care when installing the link coupler in an enclosure so that the cable connecting the SLC 500 controller to the link coupler does not hit the enclosure door. 2. Carefully plug the terminal block into the DH–485 port on the link coupler you are putting on the network. Allow enough cable slack to prevent stress on the plug. 3. Provide strain relief for the Belden #9842 cable after it is wired to the terminal block. This guards against breakage of the Belden cable wires.

A–16