Power Focus 3000: Control and Drive Unit for TENSOR-S Electric Nut Runners: User Interfaces, pages 143 to 152

Pages 143 to 152 of 315, from Power Focus 3000: Control and Drive Unit for TENSOR-S Electric Nut Runners

The original document is the PDF (7.3 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

Filed in the catalog under the Atlas Copco PF3007-C-HW and Atlas Copco PF3007-G-HW

Page 143

Configuration (Config)

10

Configuration (Config)

Click on the Config icon in ToolsTalk to view the Config window. Press the PROG button on a Power Focus 3000 Graph keyboard to enter the Config menu section. The configuration set-up contains the configuration parameters which is common for all tightenings and is unique for each Power Focus 3000 unit. Note! For more detailed Configuration parameters information see chapter 18, Parameter List.

10.1

System set-up

The System set-up contains basic Power Focus 3000 features such as name, language and the appearance of the Power Focus 3000 Graph display.

10.1.1 Password and name The password and name configuration of Power Focus 3000 is set- up in this branch. The name of a Power Focus 3000 unit may be used to identify it on a network etc. Use password protection to prevent unauthorised tampering with the controller.

10.1.2 Display set-up 1 The appearance of the Power Focus 3000 Graph display is configured in this branch. It is possible to display a number of different data.

10.1.3 Display set-up 2 The language and torque presentation unit of the Power Focus 3000 Graph display is configured in this branch. The use of Back light, soft keys and LCD viewing angle are also set-up in this branch.

10.1.4 Options The optional functions Lock on reject, Disable loosening at OK and Reset batch at Pset change are set- up in this branch.

143

Page 144

Configuration (Config)

10.1.5 Reset The buttons in this branch is used to delete all results or to perform a Total Reset. A total reset will clear all Power Focus 3000 settings including network set-up. The RBU will also be cleared. Note! Clearing the network set- up will cause Power Focus 3000 to lose contact with the network.

10.1.6 Printer Setup The connected Printer type and Paper size is set- up in this branch. Continuous print is also turned-on or off. Push the Print button on the Power Focus 3000 Graph front panel to view a list of available report to print. Note! Laser printers may not handle continuous prints, only full sheet printouts.

10.2

I/O set-up

Power Focus 3000 has extensive I/O capabilities. Apart from the internal I/O ports it is also possible to connect up to 15 external I/O devices to the Power Focus 3000 I/O bus.

10.2.1 I/O device 0-7 The function of the internal I/O ports and device 0-7 are configured in this branc h. 0: internal I/O. 1-7: external I/Os.

10.2.2 I/O device 8-15 The function of I/O device 8-15 is configured in this branch. 8-15: external I/Os.

10.2.3 Other I/Os Other inputs and outputs to the Power Focus 3000 are set- up in this branch, most notably is the Tool start select source, Job select source and the Pset select source. The Tools start source selection must be combined with correctly wired 4-pin Remote Start connector (see chapter 22, Appendix B: Description of connecting devices).

10.3

Communication

Power Focus 3000 communicates by both Ethernet and Serial communication links and can tie in with ToolsTalk and database applications such as ToolsNet, etc. IP addresses and baud rates etc are set- up in this window. 144

Page 145

Configuration (Config)

10.3.1 Remote com The IP address configuration of the Power Focus 3000 is set-up in this branch. Chapter 4, Cells and Networking, describes the networking capabilities of the Power Focus 3000.

10.3.2 Advanced com The Cell keep alive timer of the Power Focus 3000 is set in this branch. If the timer is adjusted upwards it will reduce network traffic but delay the detection of a Power Focus 3000 loosing connection with the cell. Adjusting the timer downwards will have the opposite effect.

10.3.3 Serial port set-up The serial ports of the Power Focus 3000 are set-up in this branch. The two serial ports of the Power Focus 3000 can be configured for different baud rates. Serial port 1 handles both ASCII and 3964R communication. Serial port 2 only handles ASCII communication.

10.4

Protocol

Power Focus 3000 communicates through a number of protocols. This window contains the settings for each communication protocol.

10.4.1 ToolsTalk set-up The ToolsTalk communication port is set-up in this branch. This parameter should correspond with the port number used by ToolsTalk.

10.4.2 ToolsNet set-up The ToolsNet communication is turned-on and configured in this branch. Make sure that the Power Focus 3000 is set-up in accordance with IP address and port number of the ToolsNet server.

10.4.3 Multicast set-up Multicasting of tightening results is turned-on and configured in this branch. The multicasting must be turned on in order for the Factory Overview to work. Multicasting messages uses the ToolsNet protocol.

145

Page 146

This page is a scan with no text; see it in the PDF.

Page 147

Synchronisation (Sync)

11

Synchronisation (Sync)

Click on the Sync icon in ToolsTalk to view the Sync window [the Power Focus 3000 has to be connected as a Cell master]. Push the PROG button on a Power Focus 3000 Graph keyboard to enter the Sync menu section.

With the Power Focus 3000 Gold RBU version, you have the possibility to create a Sync Group and synchronise 2 to 10 spindle s, i.e. two or up to 10 tools perform the same task simultaneously. Examples where synchronisation is used are tightening of car wheel bolts and tightening of cylinder head bolts. An Ethernet Cell must first be created [see chapter 4, Cell And Networking]. The Cell can be used as an isolated network and does not need to be connected to the factory network. Select one of the Power Focus 3000 units as the Sync Reference and use the other units as Sync Members. A Sync Group consists of 2 to 10 Power Focus 3000 units in the same Cell. One of the units in the Cell is selected as the Sync Reference and will control which Pset to run etc. The other units are called Sync Members. A Cell can be set-up with more than one Sync Group. The figure below shows an example with four synchronised Power Focus 3000 units.

The synchronisation is performed in steps where all synchronised spindles wait for each other at a number of “checkpoints” before they continue with the next step. A normal two stage tightening has checkpoints at First target and Final target. The time critical sync communication is performed over the Power Focus 3000 internal I/O-bus, which means that all units have to be connected via the I/O bus. Ethernet communication is used for non-time critical communication such as selecting Psets and transferring result data between the Sync Reference and the Sync Members. The sync function can also perform Multistage tightenings to create a synchronised tightening sequence consisting of several steps. A sync group can also be a part of a Job. For more information about accessories such as spindle -fixtures etc, please contact your local Atlas Copco representative. 147

Page 148

Synchronisation (Sync)

11.1

Setup

11.1.1 Hardware Setup Connect all Sync Members and the Sync Reference via the I/O-bus. The I/O-bus connectors are located on the back panel of the Power Focus 3000 unit. Do not connect two Sync groups via the I/O-bus and do not forget to terminate the I/O-bus with terminators. The figure below shows four Power Focus 3000 units connected via the I/O-bus.

= Termination

The 4-pin remote start connector on the Power Focus 3000 must be configured for remote start on the Sync Members and according to the selected start signal input on the Sync Reference. If an external start switch is used, connect it to the Sync Reference only. Note! Do not configure any external I/O Devices (Device 1-15) on the Sync Members.

148

Page 149

Synchronisation (Sync)

11.1.2 Parameter Setup The parameters in the table below can be reached from the Sync branch in ToolsTalk or the Power Focus Graph keyboard. The picture to the right shows the Sync parameters window in ToolsTalk.

Note! These parameters can only be programmed on the Sync Reference. A copy of the Pset are automatically transferred to the Sync Members. Parameter

Description

Sync Group List

Create a Sync Group List by selecting units from the Available Power Focus List. Select the type of loosening strategy that you want to use.

Sync loosening type

Sync loosening type

Continue if sync failed

Sync OK time

Sync loosening is a safety feature that makes all spindles sense torque before loosening starts. Normal means that all spindles are loosening with full speed and power. Select the type of loosening strategy that you want to use. Sync loosening is a safety feature that makes all spindles sense torque before loosening starts. Normal means that all spindles are loosening with full speed and power. If this option is selected the Sync Group is allowed to continue tightening with the Sync Members that reached the First target value in time. The spindles that did not reach the First target value in time are disabled. Only valid for two stage tightenings. Used together with Continue if sync failed and defines the time that the spindles in the Sync group wait, after reaching the First target value, for all spindles to reach the same status. If this time limit is exceeded, the Sync tightening continues without the spindles that did not reach the First target value in time.

149

Page 150

Synchronisation (Sync) The Parameters in the table below can be reach from the Config branch in ToolsTalk or the Power Focus 3000 Graph keyboard. Parameter

Description

Tool start select source

Sync Tool trigger: The tool trigger is used as start trigger. Reference Dig in: A digital input is used as start trigger. The digital inputs must also be configured. Warning! Do NOT use Dig in on I/O Expander*. FieldBus : The start signal is sent via FieldBus interface. Sync start : Not to be used for Sync Reference.

Sync reference IP address

Sync Sync start : All Sync Members shall be set to sync start. Members The 4-pin remote start connector on the back panel must be configured for remote start. All Power Focus 3000 units in the same Sync Group shall have the same Sync reference IP address. Note! For the Sync Reference, the Sync reference IP address shall be set equal to the IP address.

*) Note! In a synchronised application the sync communication has top priority on the I/O-bus when the tools are running. For that reason tool start, disable and other safety critical functions shall not be connected to the I/O-bus via I/O Expander. When the Synchronised Power Focus 3000 group is up and running, the Sync Reference unit alone is used for programming and selecting Pset etc. In a Sync application can I/O-bus units, such as RE-alarm, Selector and I/O Expander, only be controlled from the Sync master. On the Sync members can only the internal I/O be used.

150

Page 151

Synchronisation (Sync)

11.1.3 Step by step set-up instructions Use Ethernet connected ToolsTalk or the Power Focus 3000 Graph interface. • • •

Make sure that all Power Focus 3000 units in the Synchronised group are connected through the internal I/O-bus. Make sure that all Power Focus 3000 units in the Synchronised group are part of the same Cell [see chapter 4, Cell And Networking]. Decide which units should act as Sync Reference and Sync Members.

Sync members 1. 2. 3. 4. 5.

Set C307, Sync reference IP address. Set C220, Tool start select source to Sync start Configure the 4-pin connector on the back panel for remote start. Re-start the Sync Member Repeat step 1-4 for all Sync Members.

Sync reference 6. 7. 8. 9.

Set C307, Sync reference IP address equal to C301, IP address. Create the Sync Group List and set other Sync options. Re-start Sync Reference. Pset programming, and I/O-setup is done only on the Sync Reference.

The Synchronised Power Focus 3000 group shall now be up and running.

11.1.4 Results The status information on each controller and tool is the individual result for that spindle. The overall Sync OK / NOK can be given on FieldBus, RE-alarm or relays controlled by the Sync Reference. The results from every spindle are registered separately.

11.1.5 Event codes Event E870

Title Sync Member registration failure

E871

Sync Reference configuration failure Sync initialisation failure

E872

Description / Action Sync Member registration failed. This could be caused by two Sync Members having the same channel ID. Or by a Power Focus unit with a Sync reference IP address missing in the sync list. The Sync Reference is not first in the Sync group list. Undo the list and create it again starting with the Sync Reference. If this does not help, check the Sync Reference IP addresses. The tightening synchronisation initialisation failed. Check the CAN bus cable and check that all the Sync Members has the same active Pset. Also check the external start bridge and that the termination is ok.

151

Page 152

Synchronisation (Sync)

11.1.6 Troubleshooting Symptom Tools in a Sync group does not start

Reason / Action There are a variety of possible reasons for this behaviour. Programming-related errors: - Sync Member has not Tool start select source to Sync start. - Wrong Sync Reference IP address in the Sync Member. - No reboot after programming Hardware-related errors: - IP connection between one of the Sync Members and the Sync Reference is lost. - I/O-bus cable not correctly connected or broken. - Missing I/O-bus terminator. - The Remote start input in Sync Members not correctly wired. Error elimination: - Select a new Pset from the Sync Reference. If all Sync Members change to the same Pset, the Sync group programming is correct. If not, check the programming and the Ethernet cables and connections. - Select Normal loosening and start a Loosening from the Sync Reference. If not all Sync Members start, check the tool trigger configuration in Sync Members and the wiring of the Remote start input. Check also the I/O-bus terminator and the I/O-bus cabling. - If a single spindle does not start, the tool, tool-cable or controller might be broken. - If all Spindle in the group starts in loosening but not tightening check that all Psets are configured in the same way. If not restore them again from the Sync Reference. (all Psets shall be configured from the Sync Reference).

152