The text of a manual · part 13 of 26

CPX terminal Electronics manual: System description, installing and commissioning CPX terminals: Commissioning

Pages 95 to 106 of 221, from CPX terminal Electronics manual: System description, installing and commissioning CPX terminals

The original document is the PDF (2.2 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

Filed in the catalog under the Festo CPX-CP-4-FB

Page 95

Commissioning

Chapter 4

Festo P.BE−CPX−SYS−EN en 0503b

4−1

Page 96

4. Commissioning

Contents

4.

Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4−1

4.1 4.2

4.3

Commissioning procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4−4 Preparing the CPX terminal for commissioning . . . . . . . . . . . . . . . . . . . . . . . 4−5 4.2.1 Parameterisation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4−7 4.2.2 Possibilities of parameterisation . . . . . . . . . . . . . . . . . . . . . . . . . . . 4−10 Start−up behaviour of the CPX terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4−11

4−2

Festo P.BE−CPX−SYS−EN en 0503b

Page 97

4. Commissioning

Contents of this chapter

Further information

This chapter contains general instructions on commissioning CPX terminals. The following information in particular belongs here:

the parameterisation the address assignment the start−up reaction.

Instructions on commissioning the field bus node as well as the I/O modules can be found in the manual for the relevant module or field bus node. Instructions on commissioning the pneumatics can be found in the relevant pneumatics manual.

Festo P.BE−CPX−SYS−EN en 0503b

4−3

Page 98

4. Commissioning

4.1

Commissioning procedure In order to avoid connecting and addressing errors, you should carry out commissioning in steps as follows. The vidual commissioning steps are shown in the diagram below.

3

2

ÔÔ Ô ÔÔ Ô ÔÔ Ô ÔÔ Ô

1

1 Step 1 Checking the valve/cylinder combinations (see pneumatics manual) 2 Step 2 Checking the I/O assignment 3 Step 3 Commissioning the CPX terminal on the field bus and checking the address assignment, if necessary, without connected actuators by means of LED (see manual for CPX field bus node) Commissioning steps

4−4

Festo P.BE−CPX−SYS−EN en 0503b

Page 99

4. Commissioning

4.2

Preparing the CPX terminal for commissioning CPX terminals can be connected to various field buses. nection is made via the CPX node which is adapted to suit the relevant field bus. The reaction of the CPX terminal can be adapted to various requirements. You can carry out important settings as lows:

with the DIL switch directly on the field bus node 3.1.2).

by parameterisation (see section 4.2.1).

The DIL switch and the parameters are preset at the factory.

Caution Incorrectly set DIL switches and parameters can cause damage during operation. You must observe the following instructions in order to prevent damage.

Preparations

Festo P.BE−CPX−SYS−EN en 0503b

·

Check the DIL switch settings before using or replacing a CPX terminal.

·

Make sure that the desired parameterisation of the CPX terminal in the start−up phase or after field bus tions is carried out by the plug−in module or the scanner/ bus master, providing this is supported by the field bus protocol used. In this way you can be sure that when a CPX terminal has been replaced, the new terminal is also operated with the desired parameter settings.

Before commissioning a field bus system with CPX terminals, you should first prepare each individual CPX terminal for commissioning.

4−5

Page 100

4. Commissioning

Please note Do not connect the cables for the field bus when preparing for commissioning. You will thereby avoid:

addressing errors which may occur due to the tion of the address range during operation with various field bus systems.

Proceed with preparation as follows: 1. Check the pneumatic tubing of the valve terminals with the aid of the manual override (see pneumatics manual). 2. Check the complete electric circuitry of the CPX terminal. 3. Check the DIL switch settings of your CPX terminals (see manual for the CPX field bus node).

4−6

Festo P.BE−CPX−SYS−EN en 0503b

Page 101

4. Commissioning

4.2.1

Parameterisation The parameters are preset at the factory. These pre−settings can be used for a large number of applications. With the aid of parameterisation, the reaction of the CPX terminal or the reaction of the individual modules and I/O channels can be adapted to each particular application. The possibilities available depend on the field bus protocol used. Explanations on this can be found in the manual for the field bus node. A distinction is made between the following types of meters: Types of parameters

Description

System parameters

Influence the reaction of the complete CPX terminal

Module parameters module−specific

Influence the reaction of a particular module channel−specific

Influence the reaction of a particular input or output channel

Diagnostic memory parameters

Influence the working method of the internal diagnostic memory

Types of parameters

The individual parameters are described in detail in Appendix B.2. Basic principles of using the parameters can be found in Appendix C. The tables below give a brief overview of the most important parameters.

Festo P.BE−CPX−SYS−EN en 0503b

4−7

Page 102

4. Commissioning

System parameters

Brief description

Diagnostic monitoring with: Short circuit/overload Undervoltage in the outputs Undervoltage in the valve supply

The monitoring of short circuit and overload for the complete CPX terminal can be switched on or off with this parameter.

Signal status when there is a fault (Fail safe parameter)

Defines the status which digital output signals (outputs and valves) are to assume in the event of field bus communication faults.

Signal status in Idle mode

Defines the status which digital output signals (outputs and valves) are to assume when changing into the Idle status. This function is only relevant with certain field bus protocols (see manual for CPX field bus node).

Force signal status (force parameter)

Enables the manipulation of signal states separate from actual operating conditions and independent of the higher−order PLC/IPC.

System start

Determines the start−up behaviour of the CPX terminal

System parameters

Module−specific parameters

Brief description

Diagnostic monitoring with: Short circuit/overload Undervoltage Wire fracture

The monitoring of short circuit/overload and undervoltage on the module can be switched on or off with this parameter.

Reaction after: Short circuit/overload Wire fracture

Determines after a short circuit/overload or wire fracture whether the power is to remain switched off or whether it is to be switched on again automatically.

Input debouncing time

Serves for faultless recognition of digital input signals

Signal extension time

Serves for recognising short signals

Data format analogue values

See manual for the relevant analogue module

4−8

Module parameters part 1

Festo P.BE−CPX−SYS−EN en 0503b

Page 103

4. Commissioning

Channel−specific parameters

Brief description

Signal extension

Serves for recognising short signals

Monitoring wire fracture

Serves for recognising connection faults

Fault mode

Defines the status which the relevant channel is to assume in the event of field bus communication faults.

Fault state Idle mode

Defines the status which digital output signals (outputs and valves) are to assume when the Idle function is accessed. This function is only relevant with certain field bus protocols (see manual for CPX field bus node).

Idle state Force mode

Actual signals are replaced in the processing image by the force settings.

Force state

Module parameters part 2 Detailed information on the parameters, which are supported by the module you are using used, can be found in the ual for the relevant module. Basic principles of using the parameters can be found in Appendix C.

Diagnostic memory parameters

Brief description

Entries are remanent

Determines whether the contents of the diagnostic memory are to be retained after new Power on or whether they are to be deleted.

Diagnostic memory filters Run/Stop filter 1 + 2 Fault end filter Fault number filter Module/channel filter

With the diagnostic memory filters you can suppress the registering of certain error messages and control both the starting and stopping of the fault registering.

Diagnostic memory parameters

Festo P.BE−CPX−SYS−EN en 0503b

4−9

Page 104

4. Commissioning

4.2.2

Possibilities of parameterisation The parameterisation of the CPX terminal can be undertaken as follows depending on the field bus protocol used:

1

2

ÖÖÖÖÖ ÒÒ ÒÒ ÒÒ ÒÒ ÖÖÖÖÖ ÒÒ ÒÒ ÒÒ ÒÒ ÒÒÒÒ ÒÒÒÒ

3

4

ÔÔ ÔÔ ÔÔ ÔÔ ÔÔÔÔ 1 Plug−in module or scanner/bus master; the desired parameterisation can be guaranteed e.g. in the start−up phase or after field bus interruptions.

2 User program in the higher−order PLC/IPC; parameters can be modified during running time

3 Field bus−specific configurators; parameters can be modified during the commissioning phase or during the search for faults.

4 Handheld; parameters can be modified during the missioning phase, during the search for faults or during running time. Possibilities of parameterisation

4−10

Festo P.BE−CPX−SYS−EN en 0503b

Page 105

4. Commissioning

4.3

Start−up behaviour of the CPX terminal The desired parameterisation of the CPX terminal should be carried out in the start−up phase or after field tions by the plug−in module or the scanner/bus master, viding this is supported by the field bus protocol used. In this way you can be sure that when a CPX terminal has been placed, the new terminal is operated with the same meter settings. You can influence the start−up behaviour with the aid of the system parameter System start (see section B.2.2). Select the setting System start with default parameterisation and rent CPX equipment status." The desired parameterisation can then be carried out in the start−up phase or after field bus interruptions e.g. by the plug−in module or the scanner/bus master (depending on the field bus used). If the M−LED lights up permanently after the system start, the parameter System start with saved parameterisation and saved CPX equipment status" is set.

Caution In the case of CPX terminals on which the M−LED lights up permanently, parameterisation will not be carried out matically by the higher−order system if the CPX terminal has been replaced after servicing. In these cases check before replacing to see which settings are required and carry out these settings.

Detailed instructions can be found in the manual for your CPX node or the manual for your handheld.

Festo P.BE−CPX−SYS−EN en 0503b

4−11

Page 106

4. Commissioning

4−12

Festo P.BE−CPX−SYS−EN en 0503b