The text of a manual · part 28 of 48
SYSMAC CJ Series CJ2H-CPU6_-EIP, CJ2H-CPU6_, CJ2M-CPU_ CJ2 CPU Unit Hardware User's Manual: Section 7 Inspection and Maintenance, pages 231 to 238
Pages 231 to 238 of 422, from SYSMAC CJ Series CJ2H-CPU6_-EIP, CJ2H-CPU6_, CJ2M-CPU_ CJ2 CPU Unit Hardware User's Manual
The original document is the PDF (14 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.
Filed in the catalog under the Omron C200H-OD21A, Omron CQM1-ID211, Omron CQM1-ID213, Omron CQM1-OD211 and Omron CQM1-OD213
Page 231
Inspection and Maintenance This section describes the inspection and maintenance that is required for CJ2 PLCs.
7-1 Inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2 7-1-1 7-1-2
Inspection Points . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-2 Unit Replacement Precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-4
7-2 Replacing the Battery . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-5 7-2-1 7-2-2
Battery Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-5 Operation When Battery Is Exhausted or Not Installed . . . . . . . . . . . . . . . . . . 7-8
7-3 Power Supply Unit Replacement Time . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-10
7
CJ2 CPU Unit Hardware User’s Manual
7-1
Page 232
7 Inspection and Maintenance
7-1
Inspections Daily or periodic inspections are required in order to maintain the PLC's functions in peak operating condition.
7-1-1
Inspection Points Although the major components in CJ-series PLCs have an extremely long life time, they can deteriorate under improper environmental conditions. Periodic inspections are thus required to ensure that the required conditions are being kept. Inspection is recommended at least once every six months to a year, but more frequent inspections will be necessary in adverse environments. Take immediate steps to correct the situation if any of the conditions in the following table are not met.
Periodic Inspection Points No.
Item
Inspection
Criteria
Action
1
Source Power Supply
Check for voltage fluctuaThe voltage must be within Use a voltage tester to check the tions at the power supply ter- the allowable voltage fluctua- power supply at the terminals. Take minals. tion range. necessary steps to bring voltage fluctuations within limits.
2
I/O Power Supply
Check for voltage fluctuations at the I/O terminals.
Voltages must be within specifications for each Unit.
Use a voltage tester to check the power supply at the terminals. Take necessary steps to bring voltage fluctuations within limits.
3
Ambient environment
Check the ambient temperature. (Inside the control panel if the PLC is in a control panel.)
0 to 55°C
Use a thermometer to check the temperature and ensure that the ambient temperature remains within the allowed range of 0 to 55°C.
Check the ambient humidity. (Inside the control panel if the PLC is in a control panel.)
Relative humidity must be 10% to 90% with no condensation.
Use a hygrometer to check the humidity and ensure that the ambient humidity remains between 10% and 90%. Make sure that condensation does not occur due to rapid changes in temperature.
Check that the PLC is not in direct sunlight.
Not in direct sunlight
Protect the PLC if necessary.
Check for accumulation of dirt, dust, salt, metal filings, etc.
No accumulation
Clean and protect the PLC if necessary.
7-2
Check for water, oil, or chem- No spray on the PLC ical sprays hitting the PLC.
Clean and protect the PLC if necessary.
Check for corrosive or flammable gases in the area of the PLC.
No corrosive or flammable gases
Check by smell or use a sensor.
Check the level of vibration or shock.
Vibration and shock must be within specifications.
Install cushioning or shock absorbing equipment if necessary.
Check for noise sources near the PLC.
No significant noise sources
Either separate the PLC and noise source or protect the PLC.
CJ2 CPU Unit Hardware User’s Manual
Page 233
7 Inspection and Maintenance
No.
Item
Inspection
4
Installation and wiring
Check that each Unit is connected and locked to the next Unit securely.
No looseness
Press the connectors together completely and lock them with the sliders.
Check that cable connectors are fully inserted and locked.
No looseness
Correct any improperly installed connectors.
Check for loose screws in external wiring.
No looseness
Tighten loose screws with a Phillips-head screwdriver.
Check crimp connectors in external wiring.
Adequate spacing between connectors
Check visually and adjust if necessary.
Check for damaged external wiring cables.
No damage
Check visually and replace cables if necessary.
Check whether the battery has reached its service life.
Service life expectancy is 5 years at 25°C, less at higher temperatures.
Replace the battery when its service life has passed even if a battery error has not occurred. (Battery life depends upon the model, the percentage of time in service, and ambient conditions.)
5
User-serviceable parts
CJ1W-BAT01
Criteria
(From 0.75 to 5 years depending on model, power supply rate, and ambient temperature.)
Action
Tools Required for Inspections 7-1 Inspections z Required Tools • Slotted and Phillips-head screwdrivers • Voltage tester or digital voltmeter • Industrial alcohol and clean cotton cloth z Tools Required Occasionally
7
• Oscilloscope • Thermometer and hygrometer (humidity meter)
7-1-1 Inspection Points
CJ2 CPU Unit Hardware User’s Manual
7-3
Page 234
7 Inspection and Maintenance
7-1-2
Unit Replacement Precautions Check the following after replacing any faulty Unit. • Do not replace a Unit until the power is turned OFF. • Check the new Unit to make sure that there are no errors. • If a faulty Unit is being returned for repair, describe the problem in as much detail as possible, enclose this description with the Unit, and return the Unit to your OMRON representative. • For poor contact, take a clean cotton cloth, soak the cloth in industrial alcohol, and carefully wipe the contacts clean. Be sure to remove any lint prior to remounting the Unit. Precautions for Correct Use • When replacing a CPU Unit, be sure that not only the user program but also all other data required for operation is transferred to or set in the new CPU Unit before starting operation, including DM Area and HR Area settings. If data area and other data are not correct for the user program, unexpected accidents may occur. • Be sure to include the routing tables, Controller Link Unit data link tables, network parameters, and other CPU Bus Unit data, which are stored as parameters in the CPU Unit. Be sure to set this data again after replacing the CPU Unit. • Refer to the CPU Bus Unit and Special I/O Unit operation manuals for details on the data required by each Unit.
Additional Information The simple backup operation can be used to store the user program and all parameters for the CJ2 CPU Unit, DeviceNet Units, Serial Communications Units, and other specific Units in a Memory Card as backup files. A Memory Card and the simple backup operation can be used to easily restore data after replacing any of these Units. Refer to 8-3-6 Data Backed Up Using Simple Backup for details.
7-4
CJ2 CPU Unit Hardware User’s Manual
Page 235
7 Inspection and Maintenance
7-2
Replacing the Battery The Battery in the CJ-series CPU Unit must be replaced periodically as preventative maintenance. (The Battery is a backup power supply for the CPU Unit's internal clock and RAM). This section describes how to replace the Battery.
7-2-1
Battery Replacement
Purpose of the Battery The Battery maintains the CPU Unit internal clock and the I/O memory data held in RAM while the main power supply is OFF. If the Battery is not installed or Battery voltage drops too low, the internal clock will stop and the I/O memory data that is held will be lost when the main power supply goes OFF.
Battery Service Life and Replacement Period
The following table shows the approximate minimum lifetimes and typical lifetimes for the backup battery (total time with power not supplied). Model CJ2H-CPU6@(-EIP) CJ2M-CPU@@
Approx. maximum lifetime
Approx. minimum lifetime*1
5 years
1 year 2 months
Typical lifetime*1 5 years
*1 The minimum lifetime is the memory backup time at an ambient temperature of 55°C. The typical lifetime is the memory backup time at an ambient temperature of 25°C.
5 yr
4 year 5 months
4 yr 3 year 7 months
CJ2H-CPU6@(-EIP)
3 yr 2 yr
CJ2M-CPU@@
1 year 2 months
1 yr
25°C
40°C
Ambient temperature 55°C
This graphic is for reference only.
CJ2 CPU Unit Hardware User’s Manual
7 7-2-1 Battery Replacement
Memory Backup Time
7-2 Replacing the Battery
At 25°C, the maximum service life for batteries is five years whether or not power is supplied to the CPU Unit while the battery is installed. The battery's lifetime will be shorter when it is used at higher temperatures and when power is not supplied to the CPU Unit for long periods.
7-5
Page 236
7 Inspection and Maintenance
Low Battery Indicators If the PLC Setup has been set to detect a low-battery error, the ERR/ALM indicator on the front of the CPU Unit will flash when the battery is nearly discharged. RUN ERR/ALM INH PRPHL COMM BKUP
If the Battery Error Flag (A402.04) is ON*1, first check whether the Battery is properly connected to the CPU Unit. If the battery is properly connected, replace the battery as soon as possible. Once a low-battery error has been detected, it will take 5 days (at an ambient temperature of 25°C*2) before the battery fails assuming that power has been supplied at least once a day. Battery failure and the resulting loss of data in RAM can be delayed by ensuring that the CPU Unit power is not turned OFF until the battery has been replaced. *1 The Battery Error Flag (A402.04) will turn ON only if the Detect Low Battery parameter in the PLC Setup has been set to detect a low-battery error. If this setting has not been made, battery errors will not be detected. *2 The battery will discharge faster at higher temperatures, e.g., 4 days at 40°C and 2 days at 55°C.
z Replacement Battery Use the CJ1W-BAT01 Battery Set. Precautions for Correct Use Be sure to install a replacement battery within two years of the production date shown on the battery's label. Production Date CJ1W-BAT01
08-06
Manufactured in June 2008.
Replacement Procedure Use the following procedure to replace the battery when the previous battery has become completely discharged. Precautions for Safe Use We recommend replacing the battery with the power OFF to prevent the CPU Unit's sensitive internal components from being damaged by static electricity. The battery can be replaced without turning OFF the power supply. To do so, always touch a grounded piece of metal to discharge static electricity from your body before starting the procedure. After replacing the battery, connect a Programming Device and clear the battery error.
1 Turn OFF the power to the CPU Unit. If the CPU Unit has not been ON, turn it ON for at least five minutes and then turn it OFF.
7-6
CJ2 CPU Unit Hardware User’s Manual
Page 237
7 Inspection and Maintenance
Additional Information If power is not turned ON for at least five minutes before replacing the battery, the capacitor that backs up memory when the battery is removed will not be fully charged and memory may be lost before the new battery is inserted.
2 Open the compartment on the upper left of the CPU Unit and carefully draw out the battery.
• You must complete this procedure within five minutes at 25°C after turning OFF the power to the CPU Unit to ensure memory backup. Data may be lost if more than five minutes is required. • Never short-circuit the battery terminals; never charge the battery; never disassemble the battery; and never heat or incinerate the battery. Doing any of these may cause the battery to leak, burn, or rupturing resulting in injury, fire, and possible loss of life or property. Also, never use a battery that has been dropped on the floor or otherwise subject to shock. It may leak. • UL standards require that batteries be replaced by experienced technicians. Always place an experienced technician in charge or battery replacement.
Additional Information The battery error will be cleared automatically the next time the CPU Unit is turned ON after replacing the Battery.
CJ2 CPU Unit Hardware User’s Manual
7-7
7 7-2-1 Battery Replacement
• Turn ON the power after replacing the battery for a CPU Unit that has been unused for a long time. Leaving the CPU Unit unused again without turning ON the power even once after the battery is replaced may result in a shorter battery life.
7-2 Replacing the Battery
Precautions for Safe Use
Page 238
7 Inspection and Maintenance
7-2-2
Operation When Battery Is Exhausted or Not Installed The CJ-series PLCs can operate even when the Battery is exhausted or not installed.
Continuing Operation To have operation continue when the Battery is exhausted or not installed, set the parameter in the PLC Setup so that Battery errors are not detected.
Saving Data The user program and parameter area data are saved in flash memory even when the Battery is exhausted or not installed. I/O memory (such as the CIO Area), however, cannot be saved.
Conditions for Operation Operation is possible when the Battery is exhausted or not installed if the following two conditions both apply. • There is no need to save data in I/O memory. • There is no need to use initial settings in the DM/EM Area, or the initial settings are made by the user program. Additional Information You can use the function for automatic transfer from the Memory Card at startup to store data in I/O memory and the DM/EM Area even when the Battery is exhausted or not installed. The following table shows when the Battery is required according to the purpose of CPU Unit operation. Saving I/O memory is required.
Saving to I/O memory is not required.
DM/EM Area initial values are required at startup.
The Battery is required. DM/EM Area initial values are set from the Memory Card. DM/EM Area initial values are set from the user program.
DM/EM Area initial values are not required at startup.
Automatic transfer from the Memory Card at startup is set. (Pin 2 is set to ON.) Normal operation from flash memory or operation using the Memory Card is possible.
Restrictions • The clock function cannot be used, so the values for the Calendar/Clock Area (A351 to A354) and the Startup Time (A510 to A511) in the Auxiliary Area will be unstable. In addition, the times at which the CPU Unit created files on the Memory Card will be unstable. • The Total Power ON Time (A523), Power Interruption Time (A512 to A513), and Number of Power Interruptions (A514) in the Auxiliary Area will all be all zeros at startup. • Error log data will not be held in the Error Log Area (A100 to A199) in the Auxiliary Area at startup. • Correct values may not be held in I/O memory (including the HR, DM, and EM Areas) at startup. In the PLC Setup, set the IOM Hold Bit (A500.12) and the Forced Status Hold Bit (A500.13) to not be held at startup.
7-8
CJ2 CPU Unit Hardware User’s Manual